DISCLAIMER
Every reasonable effort has been made to ensure the accuracy of the information provided; nevertheless, some information may not be accurate. Confirmation is recommended as there may be errors in the database.


Neighborhood Lookup: Waterfront: West Beach: Pending and Approved Projects

View Case Status

Case Number: MST2015-00348 Status: Application has been Submitted, no Final Action to-date
Application Date: 7/10/2015
Description: Courtesy review of a new Campus Center at Santa Barbara City College. The proposal consists of the demolition of an existing 30,384 square foot, two-story building and construction of a new, three-story, 32,384 square foot Campus Center on the east campus.
Address: 721 CLIFF DR

Reverse Sorted by Completed Date

Case Activities

Type Completed
ABR-FYI/Research 9/7/2016
ABR-Concept Review (New) 7/20/2015
Application Received 7/10/2015

Back Print this Page Top of Page