DISCLAIMER
Every reasonable effort has been made to ensure the accuracy of the information provided; nevertheless, some information may not be accurate. Confirmation is recommended as there may be errors in the database.


Neighborhood Lookup: Mesa: West Mesa: Pending and Approved Projects

View Case Status

Case Number: MST2016-00191 Status: Application has been Submitted, no Final Action to-date
Application Date: 5/5/2016
Description: This is a revised project description. Proposal to demolish an existing 1,697 square foot single residential unit with a detached 490 square foot two-car garage and an unpermitted 170 square foot carport and construct a new single residential unit. The proposal consists of a new 3,469 square foot two-story single residential unit with a 400 square foot attached two-car garage. Other site improvements include a new driveway and motor court, front porch, covered loggia and landscaping. The proposed total of 3,869 square feet of development on a 20,070 square foot lot located in the Hillside Design District is 82% of the guideline maximum floor-to-lot area ratio (FAR). The project requires Planning Commission approval of a Coastal Development Permit.
Address: 2327 EDGEWATER WAY

Reverse Sorted by Completed Date

Case Activities

Type Completed
(F) Print S F D B Activities 7/17/2019
(F) Print S F D B Activities 2/28/2019
(F) Print S F D B Activities 2/28/2019
BLD DART #3 Draft Comments 2/4/2019
SFDB-Concept Review (Cont.) 9/17/2018
SFDB-Resubmittal Received 9/10/2018
SFDB-Concept Review (Cont.) 8/20/2018
SFDB-NoticePrepared-PC/SHO Req 8/15/2018
SFDB-Resubmittal Received 8/9/2018
SFDB-Resubmittal Received 8/3/2018
PC-Case Planner Status 8/3/2018
PC-DART Deemed Complete 3/24/2017
BLD DART #2 Draft Comments 2/27/2017
SFDB-Concept Review (Cont.) 11/28/2016
SFDB-Resubmittal Received 11/21/2016
SFDB-Resubmittal Received 11/17/2016
SFDB-Concept Review (Cont.) 11/14/2016
SFDB-Resubmittal Received 11/2/2016
SFDB-Resubmittal Received 10/24/2016
SFDB-Mailed Notice Prepared 9/19/2016
SFDB-Concept Review (New) - PH 9/19/2016
SFDB-FYI/Research 9/12/2016
(F) Print Prelim Plan Check 9/7/2016
Prelim Plan Check - Zoning 9/7/2016
(F) Design Review Routing 8/24/2016
SFDB-Resubmittal Received 8/19/2016
BLD DART #1 Draft Comments 5/24/2016
PC-Posting Sign Issued 5/5/2016
Application Received 5/5/2016
PC-DART Incomplete  
PC-DART Received  
PC-DART Received  

Back Print this Page Top of Page